Business Opportunity

IFB 17-001 Installation of 50KW Electric Bus Charging Station

Start Date: 08/24/2016
End Date: 09/07/2016

The PVTA is seeking sealed bids for installing a proprietary 50KW electric bus charger and related equipment within PVTAs existing Springfield Maintenance Garage.The work involves installation of a pre-manufactured Eaton DC Quick Charger at a pre-determined location within the maintenance garage, set onto a new concrete equipment pad, with new conduit and wiring connections to an existing nearby electric service panel, new painted safety signage onto the adjacent existing masonary wall, new safety striping on the floor, and installation of 2 new steel bollards to be surface mounted to the existing concrete slab. The existing 50KW Charger is currently being stored on-site.

Download Documents


Return to Business Opportunities.